Network Upgrade Project
8 entries, newest to oldest
18 October, 2026 at 7:00 AM AEST
[Scheduled] Access Switches Upgrade - Joyce Ackroyd 01-0037 TR521
Scheduled for 2026-10-18 07:00:00 - 2026-10-18 22:00:00 ITS will be installing 2 x C9407R and 1x C9200CX access switches into rack A, B in Joyce Ackroyd 01-0037 TR521.
27 September, 2026 at 7:00 AM AEST
[Scheduled] Access Switches Upgrade - Michie 01-0009 TR115 and Duhig 01-0002 TR d701
Scheduled for 2026-09-27 07:00:00 - 2026-09-27 22:00:00 ITS will be installing 2 x C9348 access switches into rack A 01-0009 TR115 and 1 x C9348 access switches into rack A 01-0002 TR d701. Resolution …
20 September, 2026 at 7:00 AM AEST
[Scheduled] Access Switches Upgrade - JD Story 01-0061 TR602
Scheduled for 2026-09-20 07:00:00 - 2026-09-20 22:00:00 ITS will be installing 1 x C9407R access switch into rack A 01-0061 TR602. Resolution Upgrade completed successfully (22:00 AEST — Sep 20)
5 September, 2026 at 6:00 AM AEST
[Scheduled] JD Story 01-0061 TR502 - Access Switches Upgrade
Scheduled for 2026-09-05 06:00:00 - 2026-09-05 22:00:00 Install 1x C9407R into rack A in 01-0061 TR502. Connect new 01-0061-502-as01 to the Agg routers Install and connect the new 2x32A power supplies …
23 August, 2026 at 7:00 AM AEST
[Scheduled] Access Switches Upgrade - JD Story levels 3 & 4
Scheduled for 2026-08-23 07:00:00 - 2026-08-23 22:00:00 Install 2x C9407R access switches into rack A 01-0061 TR301a & TR402. Connect new 01-0061-301a-as01 and 01-0061-402-as01 to the Agg routers …
16 August, 2026 at 7:00 AM AEST
[Scheduled] Access Switches Upgrade - JD Story level 2
Scheduled for 2026-08-16 07:00:00 - 2026-08-16 22:00:00 ITS will be removing Rack B and installing 1x C9407R access switches into rack A 01-0061 TR202. Resolution Network successfully upgraded (22:00 …
9 August, 2026 at 7:00 AM AEST
[Scheduled] JD Story Level 1 Access switches upgrade
Scheduled for 2026-08-09 07:00:00 - 2026-08-09 22:00:00 ITS will be installing 2 x C9348 access switches into rack A 01-0061 TR102A. Resolution Network upgrade completed successfully (22:00 AEST — Aug …
19 July, 2026 at 7:00 AM AEST
[Scheduled] Gatton Library Network Upgrade - 1 x 9407/3 access switches into rack B 29-8102 TR120.
Scheduled for 2026-07-19 07:00:00 - 2026-07-19 22:00:00 ITS will be installing 1 x 9407/3 access switches into rack B 29-8102 TR120. Resolution Network switch upgrade completed successfully (22:00 …