10 March, 2024 at 10:30 AM AEST

[Scheduled] Emergency Downgrade of APIC and Gen 2 Leaf switches in Prentice DC  

Scheduled for 2024-03-10 10:30:00 - 2024-03-10 15:30:00 Due to failed CR13641 the Prentice ACI Fabric now in a mixed non-supported mode, we need to reverse the change and rollback the 3 APICs and 8 …
9 March, 2024 at 6:00 AM AEST

[Scheduled] APIC Upgrade and Leaf Switch Upgrade/Replacement in the Prentice Next Gen DC  

Scheduled for 2024-03-09 06:00:00 - 2024-03-10 20:00:00 This is again a multi-stage change over 2 days. a) APIC Software Upgrade will start on 06:00 AM on Sat 9th March and expected to be completed by …
2 March, 2024 at 8:00 AM AEST

[Scheduled] PRNDC ACI - CIMC-APIC And Gen2 Leafs Firmware Upgrade  

Scheduled for 2024-03-02 08:00:00 - 2024-03-03 20:00:00 This is the first Stage of the PRNDC ACI Upgrade: This includes software update of CIMC and three APIC controllers, followed by software update …