[Scheduled] PRNDC ACI - CIMC-APIC And Gen2 Leafs Firmware Upgrade

2 March, 2024 at 8:00 AM AEST

NGDC Serverfarm


Scheduled for 2024-03-02 08:00:00 - 2024-03-03 20:00:00

This is the first Stage of the PRNDC ACI Upgrade:

This includes software update of CIMC and three APIC controllers, followed by software update of Eight Gen2 leaf switches.

Timelines:

a) CIMC Firmware Upgrade, will start at 8:00 AM on 2nd March, which is likely to continue for 6 hours to complete for all the apic nodes.

b) APIC Software Upgrade will start on 08:00 AM on 3rd March and expected to be completed by 3:00 PM

c) Gen2 Leaf switch upgrade will commence on 4:00 PM on 3rd march. These will be done in two groups of leaf switches, which may likely take 4 hours.


Resolution Automatic resolution. (20:00 AEST — Mar 3)