[Scheduled] APIC Upgrade and Leaf Switch Upgrade/Replacement in the Prentice Next Gen DC

9 March, 2024 at 6:00 AM AEST

NGDC Serverfarm


Scheduled for 2024-03-09 06:00:00 - 2024-03-10 20:00:00

This is again a multi-stage change over 2 days.

a) APIC Software Upgrade will start on 06:00 AM on Sat 9th March and expected to be completed by 11:00 AM

b) Gen2 Leaf switch upgrade will commence on 11AM on Sat 9th March. These will be done in two groups of leaf switches, which may likely take 4 hours.

c) Four (4) Leaf Switches are to be replaced 1 by one. No Outages are expected if the servers are dual connected.

Timelines: This is a two-day activity. Will target to achieve switch replacement for two racks in each day and if time permits, it will be three rack. Starting at 06:00 AM on 9th March and finishing on 06:00 PM and then again starting on 10th march at 06:00 AM and continue.


Resolution Automatic resolution. (20:00 AEST — Mar 10)