[Scheduled] Access Switches Upgrade - JD Story levels 3 & 4

23 August, 2026 at 7:00 AM AEST

Network Upgrade Project


Scheduled for 2026-08-23 07:00:00 - 2026-08-23 22:00:00

  1. Install 2x C9407R access switches into rack A 01-0061 TR301a & TR402.
  2. Connect new 01-0061-301a-as01 and 01-0061-402-as01 to the Agg routers
  3. Connect the new access switch to 2x32A power supplies.
  4. Patch and configure.

Resolution Upgrade completed successfully on levels 3 & 4 (22:00 AEST — Aug 23)

Last updated: 23 August, 2026 at 7:00 AM AEST